ACC Strategy Team Recommendations Timeline
From left to right, view our anticipated timeline for strategy team recommendations and the beginning of implementation.
March 31
Strategy Team Action Plans Due
April 7-28
Nucleus Team and Stakeholder review and score strategic action plans.
April 29
Prioritize action plan recommendations. Decide on themes that can be implemented across multiple strategies.
May 1
Develop and implementation timeline
May 12
Nucleus Team to review strategy implementation priority with Deans and make adjustments
May 26
Finalize recommendation report for Cabinet / Core Team
June 3
Review recommendations with Cabinet
June 16
Share approved recommendations with strategy teams
Fall 2025 BCC Week
Share strategy team recommendations with the College